Kirkwood Place May Update

2017-05-12 00:00:00

Kirkwood Place is progressing on schedule. The roof is on, framing has been completed, exterior residential doors and windows are in and plumbing, HVAC, electrical and fire sprinkler rough-ins are complete. Exterior insulated sheathing is underway and masonry will start May 21st. Insulation will start next week and drywall should start in about a week. Site work is ongoing.